If you're carrying out work that requires building control, you must send us a completion notice within five days of completing the work. The client, agent or builder can do this.

We will not visit your site for a completion inspection until we’ve received this notice.

Before you submit a completion notice, you or your builder will need to supply certain test results or certificates. For a domestic extension, this may include:

  • electrical installation certificate
  • fire alarm installation and commissioning certificate
  • gas certificate
  • double-glazing specification

Download and submit the completion notice:

We need this notice before we inspect the completed work or issue a completion certificate. 

Completion certificate

We will issue a completion certificate once we: 

  • have received all the certificates
  • are satisfied that you have complied with regulations

Keep this safe as you'll need it if you wish to remortgage or sell the property.